Timber posts in concrete sockets, sleepers and timber decking
Scope
Dismantling and construction of a new platform
BeforeAfter
From drawing to site
The platform, rebuilt.
The old platform around the pink tower was spent: rotten posts and worn boards. It was taken down and a new one built, with timber posts in concrete sockets, sleepers and new decking.
01DismantlingThe old platform and its posts come out
02Posts in socketsTwin timber posts set in concrete sockets
03SleepersTimber frame every 1.25 m
04DeckingStage 2 (23.91 m²) and stage 3 (146.62 m²)
Illustrative model: outline and posts taken from the plan; dimensions are approximate.
Before: the original ramp and platform
Before: damaged posts
Before: the original frame
Process